PRINCE2 7 Foundation · Study lesson 23
Name uncertainty and ownership
Describe what might happen, why it matters and who will manage it.
9 minute study lesson · Practices · Original learning material
What you will understand
- Distinguish a threat from an opportunity and an issue.
- Describe a risk using cause, event and effect.
- Distinguish risk ownership, action ownership, appetite and tolerance.
The idea
“Supplier risk” is too vague to guide a decision. A useful risk description explains what is uncertain, why it might happen and what objective would be affected. Risk management considers both threats and opportunities. Naming the uncertainty clearly makes it possible to assess it, choose proportionate action and assign ownership before its consequences arrive.
A risk involves uncertainty that could affect objectives. A threat has a potentially negative effect; an opportunity has a potentially positive effect. A late delivery that has already happened is no longer merely the uncertainty that it might happen: the current situation needs issue management, while any uncertain further consequences remain risks. Do not remove the earlier history, because it helps explain the response and informs future learning.
Separate cause, event and effect. A cause is the existing source of uncertainty, such as dependence on one specialist. The event is what might occur, such as that specialist becoming unavailable during commissioning. The effect is the consequence for an objective, such as delaying opening by two weeks. This structure prevents a general worry, an existing fact and a potential consequence from being treated as interchangeable descriptions.
Assess likelihood, impact and proximity using the agreed scales. Likelihood concerns the chance of the uncertain event; impact concerns its effect on objectives if it occurs. Proximity concerns when the risk could occur, so a modest risk requiring action tomorrow may demand attention before a larger one several months away. Exposure expresses the potential effect of uncertainty and may concern either positive or negative consequences. Consider the combined position as well as individual entries.
Risk appetite expresses the amount and type of risk the business is willing to take in pursuit of its objectives. Risk tolerance provides measurable boundaries for acceptable variation in objectives at risk. These are related but different: a general willingness to experiment does not authorise exceeding a particular project’s agreed safety, cost or other limits. Risk decisions need the appropriate authority and must remain consistent with the business context.
A risk owner manages and monitors an identified risk and ensures that a suitable response is considered and followed through. A risk action owner, also called an actionee, carries out a specified response action. The same person can hold both responsibilities when appropriate, but an action assignment does not automatically transfer the whole risk. The risk management approach defines the procedures, roles, scales and reporting arrangements; the risk register records the actual risks and their evolving assessment, ownership, responses and status.
Describe uncertainty clearly
| Component | Example |
|---|---|
| Cause | A scarce component has only one available supplier. |
| Uncertain event | The supplier may miss the delivery date. |
| Effect | Installation could slip and increase costs. |
| Risk owner | Manages the risk and monitors the agreed response. |
| Risk action owner | Carries out a specified response action. |
An original fictional example
Fictional example: a riverside workshop opening
A workshop has one certified person able to commission its extraction system. That person may be called to another site during the opening week, which could delay safe opening. The facilities lead owns the risk. A purchasing officer is assigned to investigate availability of a second qualified provider by Friday.
The decision
Record the dependency as the cause, possible unavailability as the event and delayed opening as the effect. Keep overall monitoring with the facilities lead and the investigation action with purchasing.
Why it makes sense
The description identifies a specific uncertainty and objective. Separate ownership makes both continuing oversight and the immediate response action visible.
A common confusion
The mistaken idea: The person given one risk response task automatically becomes responsible for managing the entire risk.
The distinction: Action ownership concerns the assigned response. Risk ownership concerns continuing management and monitoring of the risk, unless that ownership is explicitly reassigned.
Own the uncertainty; assign the actions.
Points to remember
- Risk can mean a threat or an opportunity.
- Cause, uncertain event and effect on an objective are distinct.
- Proximity describes timing, while probability describes likelihood.
Your takeaway
Describe uncertainty precisely, assess it using agreed measures and give it a suitable owner. Distinguish appetite from measurable tolerance, and distinguish ownership of the whole risk from responsibility for a particular action.
This independently written explanation is supplementary study material. It is not official examination content. Read about our content and its limitations.