PRINCE2 7 Foundation · Study lesson 30
Give authority at decision points
Understand the board’s continuing role without confusing it with daily management.
10 minute study lesson · Processes · Original learning material
What you will understand
- Identify the principal authorisation decisions in Directing a project.
- Distinguish board direction from project manager coordination.
- Recognise when project-level concerns require business-level authority.
The idea
The project board should be available when an important decision is needed, even when it is not meeting every day. Directing a project describes how the board exercises governance across the project. It connects decisions about investment and authority with day-to-day management delegated to the project manager. The board remains accountable while allowing the manager to manage.
Direction begins with considering whether to authorise initiation. The board examines the project brief and the proposed initiation stage plan before committing resources to that preparation. This differs from authorising the project after initiation. The later decision considers the project initiation documentation, the developed business case and the proposed delivery arrangements. The two decisions answer different questions and can have different outcomes.
The board also authorises a stage or an exception plan. At a normal boundary, the decision uses evidence about the stage ending, the updated outlook and the next stage plan. Where a forecast breach requires replacement planning, an exception plan may be requested and assessed. Authority should identify the relevant plan, resources and tolerances. A favourable conversation does not silently authorise every later stage or any future change.
Giving ad hoc direction allows the board to respond between planned decision points and to communicate relevant business information. Direction may be needed because priorities change, an exception is raised or a stakeholder concern affects the project. The board can support the project manager and resolve matters at its level. It should avoid taking over routine task allocation, which belongs within the delegated management arrangements.
Authorising project closure is another board decision. The project manager prepares the closure recommendation and evidence; the board considers whether suitable acceptance, handover, evaluation and follow-on arrangements are in place. Products being delivered does not make closure automatic. Equally, a project can require controlled premature closure if its justification disappears. Direction must accommodate stopping responsibly as well as continuing responsibly.
The executive represents business accountability, with senior user and senior supplier interests informing the board’s decisions. Assurance helps the board obtain confidence independently of project management. If the forecast exceeds project-level tolerances granted by the commissioning business, the board cannot simply enlarge its own delegated authority. It must seek a decision at the business level while making the implications clear to the project manager.
Direction spans the project
| Board decision | Information it considers |
|---|---|
| Authorise initiation | Whether further definition is worth the investment. |
| Authorise the project | Whether the established foundations justify delivery. |
| Authorise a stage or exception plan | Whether the next proposed commitment is justified. |
| Give direction as needed | Advice and decisions within the board’s authority. |
| Authorise closure | Whether controlled closure is appropriate. |
An original fictional example
Fictional case: a theatre’s accessible entrance
The project manager has completed initiation for a new entrance. The board receives the management baseline and the first delivery stage plan. A supplier asks the board to assign individual installation tasks directly to the trades team.
The decision
The board considers the business case and authorisation request, sets the stage authority if it approves, and leaves work package coordination to the project manager. It remains available for direction and escalations.
Why it makes sense
Investment authorisation belongs to direction. Daily coordination belongs to project management and team delivery. Clear separation supports both accountable decisions and efficient working.
A common confusion
The mistaken idea: Directing a project is a single approval before delivery begins.
The distinction: The board directs throughout the lifecycle through authorisations, ongoing direction and the closure decision.
Think of a continuing governance thread, not one box at the start.
Points to remember
- The board authorises initiation, the project, stages or exception plans, and closure.
- Ad hoc direction can occur between planned decision points.
- The board delegates daily management without surrendering its accountability.
Your takeaway
Directing a project keeps investment decisions and delegated authority explicit throughout the lifecycle. Match the decision to the right level and keep routine coordination with the manager.
This independently written explanation is supplementary study material. It is not official examination content. Read about our content and its limitations.